The Borrowed Republic (Part 3): What The World Bank Itself Said About Its Own Money In Nigeria

By Matthews Otalike, The Searchlight Investigative Desk / November 21, 2026

In Part 1, we asked: Where did the loans go? In Part 2, we published the figures: $700m for girls, $500m for women, most of it undisbursed. Abuja said nothing. So, in Part 3, we beamed The Searchlight on Washington. Not to enemies of Nigeria, but to the lender itself, the World Bank.

What we found is shocking: The World Bank has been telling Nigeria, in its own official Implementation Status And Results Reports (ISRs), that its money is not working. That implementation is slow. That capacity is low. That political interference, bureaucracy, and staff turnover are killing the projects. The lender has indicted the borrower and the borrower is still asking for another $21.67.

  1. AGILE, THE GIRLS’ PROJECT: “SLOW IMPLEMENTATION REMAINS AN OBSTACLE”. This is not The Searchlight speaking. This is the World Bank’s ISR for AGILE, the $1.2 Billion Adolescent Girls Initiative (original $500m in 2020 + additional $700m in September 2023). This is what the Bank wrote, verbatim: “The slow implementation of critical project activities remains an obstacle for some states. The inefficient performance of lagging states could undermine project progress. These states have shown low capacity in implementing critical activities such as fiduciary, monitoring and evaluation, reporting, and project management.” “Security challenges remain pervasive across some states, making it difficult to implement and supervise the implementation of project activities.” “Bureaucratic processes and changes in SPIU staff continue to cause delays in the implementation of project activities in some of the project states.”

And because of that, the Bank had to order every State Project Implementation Unit to hire a security consultant just to be able to visit schools. Let us translate that English, Sir: The Bank gave Nigeria $1.2 Billion for girls. Nigeria could not spend it because states could not manage the money, could not report properly, kept changing staff, and could not even guarantee security for its own officials to supervise schools. Yet, in the same report, the Bank records a small light: 20 schools completed, 258 schools under construction, 2,112 classrooms to be added across four states. 20 schools. For $1.2 Billion promised. For millions of girls waiting. If this is success, what is failure?

2. NIGERIA FOR WOMEN: “DELAYS IN PROJECT IMPLEMENTATION AND STAFFING GAPS “For the Nigeria For Women Project, the Bank’s Restructuring Paper (March 26, 2024) admits the same disease. It records “delays in project implementation and staffing gaps” in states like Abia, and notes that Abia only “expects to conclude payments of individual livelihoods grant by April 30, 2024”, years after the project started in 2018. The Bank’s own Procurement Strategy for the Scale-Up ($500m) warns in advance about what will go wrong again: “Political interference and Interest”

“Lack of political will on the part of politicians””Low capacity of FPCU and SPCUs”. The Bank knew. It wrote it down. It lent the money anyway. And yet, in November 2026, the National Coordinator, Dr. Hadiza Maina, told Nigerians that the programme has 86,000 Women Affinity Groups, 1.8 million members, N22 Billion mobilized in savings, N2.4 Billion disbursed in Community Investment Funds across three states. Now, The Searchlight is asking: If 1.8 million women are in the programme, why does the disbursement rate remain so low? If N22 Billion was saved by the women themselves, what did the $500 Million loan add? Where is the list of the 86,000 groups, LGA by LGA? The Bank’s reports praise the idea and the Bank’s reports also condemn the execution.

In May 2025, the Bank’s Aide Memoire recorded the following: Disbursement to date: $0.0. Undisbursed: $500.0 million. Program Status: Not yet effective. Eight months after approval, nothing had moved. By November 2025, only $3 Million had been disbursed, all from the $20 Million support component. None of the $480 Million results-linked money had been disbursed. Yet in November 2026, at the Lagos review meeting, the Bank’s own Task Team Leader, Ikechukwu Nweje, admitted publicly that: “The initial performance has not been as good as we expected.” “The programme has run for about two years but faced delays, so only one round of verification has been done.”

The July 2026 ISR downgraded Implementation Progress from Satisfactory to Moderately Satisfactory, and kept Overall Risk Rating at High. Political and Governance Risk: High. Macroeconomic Risk: High. What this translates to is that the Bank gave $500 Million to fix how states budget for teachers and health workers. Two years later, most states still cannot prove they did the reforms.

4. THE PATTERN: IT IS NOT ONE PROJECT. IT IS THE SYSTEM. The Digital ID Project for which $430 Million was approved in February 2020 is now on its THIRD extension, 42 months of extra time. $196 Million still remains undisbursed. Enrolment partners have been not paid since January 2026. The targeted NIN to be produced is 180 million. As at Sept 30, 2026 121 million have been produced leaving a deficit of 59 million NINs. The Federal Government itself has already admitted it years ago.

Former Minister of Finance, Zainab Ahmed, told the National Assembly that “Delays in the execution of donor-funded projects stems from factors including bureaucratic bottlenecks, capacity challenges, political interference and challenges associated with obtaining varied and misaligned approval processes.” In May 2026, the Accountant-General of the Federation, Dr. Shamseldeen Ogunjimi, warned the World Bank itself that “If approvals take more than six months, the Nigerian Government may no longer honour such arrangements.” He complained about delays and the Bank replied, in effect that “Our loans are not released in lump sums. They are tied to milestones. If you do not meet the milestones, we do not release the money. Both sides are blaming each other. And in the middle of the argument, the Nigerian girl is out of school, the Nigerian woman is without capital, the Nigerian patient is without a health centre.

5. THE SEARCHLIGHT’S VERDICT: This is why Part 3 of our analysis matters more than Part 1 and Part 2. We are no longer saying “The money is missing.” The Bank itself says “The money is not moving. “We are no longer saying “The government is failing.” The government itself had told the National Assembly that implementation is low because of political interference. The question is no longer: Did we borrow? We did. The question is no longer: Did we receive? We received only a fraction.

The question now is: Why does a country that cannot spend $500 Million for women, $700 Million for girls, and $500 Million for HOPE, want to borrow another $21.67 Billion? To borrow more when you cannot spend what you have is not development. It is debt slavery for our children. The World Bank must also answer: Why do you keep approving billions for a system your own reports say has low capacity, high political interference, and high risk? Is it lending, or is it a trap? The Searchlight demands the following:

1. Publish ALL Implementation Status Reports for AGILE, NFWP-SU, HOPE-GOV, and Digital ID on the Federal Ministry of Finance website, not just on the World Bank website in Washington.

2. Publish the names of the lagging states the Bank identified, the states with low capacity that are undermining the projects. 3. Stop all fresh borrowing until the undisbursed balances, over $4 Billion from Tinubu-era approvals alone, are accounted for and spent. We will keep the light on. We will keep quoting the Bank to the Bank, and the Government to the Government. Until the girls go to school. Until the woman in in the village gets her capital, and until the money moves from paper to people